Konačni dizajn mosta Brekovica

Final design of the Brekovica bridge over Una river at regional road Brekovica – Bihać
Spans and total length: L=20,90+21,20+20,9=63,00m
Construction method: composite precast T beams with monolithic slab
Material of superstructure: prestressed concrete
Client: Public Company Roads Federation of Bosnia and Herzegovina
Location: Brekovica, intersection of regional and major road M14
Date: from December 2014 to January 2015

PRELIMINARNA REHABILITACIJA I PRODUŽENjE PROJEKTOVANJE TREBINACIONOG OBJEKTA TREBINJE 50.000 PE

Preliminary design development activities: • Geodetic site survey
• Hydraulic analysis and study
• Drafting of the technical report and BoQ
• Development of technical solutions and working drawings
Date: 2014