logo

Monthly Archives: October 2016

The Karaula Tunnel within the Kladanj – Podpaklenik section of trunk road Tuzla-Sarajevo

The Karaula Tunnel within the Kladanj – Podpaklenik section of trunk road Tuzla-Sarajevo, is 902 meters long, the evacuation tunnel 435 meters and the road in advance of and after the tunnel 1,195 meters. The project works were executed between June 2014 and September 2016. The Client is JP Ceste FBiH, the Contractor Strabag AG from Austria and the Sub-Contractor Entea d.o.o. Sarajevo. Construction supervision in line with the 1999 Edition of the FIDIC Red Book was carried out by […]